News from WerkHuus1 โ Update January 2026 ๐ข
The new year starts with a lot of movement on the construction site of our office building WerkHuus1. Step by step, what has been planned, coordinated and implemented in recent months becomes visible – and the progress is impressive. ๐ง
The current status:
โ
The scaffolding was already completely dismantled at the end of December 2025
๐ This week: Laying of the screed on the ground floor
๐ The ceiling substructure of the suspended ceilings in the future meeting zones is currently being completed
โ
The bathrooms are mostly tiled
โ
The painting work has been completed
โ
on the top two floors The double floor is completely finished
๐ The installation of the elevator will start next week
โ
The exhaust air technology below the ceilings has been installed
โ
The absorption system (an impressive 2.3 tonnes) has found
โ
its place in the basement, the ventilation system and complete power distribution in the basement are currently under construction
Each of these steps brings us closer to a modern, functional and lively working environment.
We look forward to continuing to take you with us and sharing even more insights soon. ๐
#UnternehmensgruppeTerhalle #WerkHuus1 #BaustellenUpdate #Januar2026 #Bรผrogebรคude #Projektfortschritt