Precise planning and perfect timing are essential when it comes to company …

Precise planning and perfect timing are essential for the Terhalle Group. ⏱️

In this video, Tom Wissing, Head of CAD, and Daniel Kemmer, Team Leader Work Preparation, explain the individual steps from the start of work phase 4 or 5 to the construction site. 🏡

An important factor here is also the ordering of materials in the AV. “We don’t have the lead time or the storage capacity to prefabricate the entire building and then bring it to the construction site,” explains Daniel Kemmer. “It has to be manufactured in the same order as it will be built afterwards.” 🏗️

#CompanyGroupTerhalle #CADPlanning #WorkPreparation #TeamTerhalle