🏗️ Update Sports Hall Vreden
Completed work:
• Completion of the roof structure including 200 m² of wooden beam ceiling and 500 m² of outer walls
• Installation of 500 m² of clay
façade tiles• Installation of 1,800 m² of trapezoidal sheet metal
Ongoing work:
• The warm roof trapezoidal sheet metal is currently being installed
Outstanding work:
• Implementation of the green roof with PV substructure
• Production of the 600 m² warm roof on the concrete ceiling
• Installation of 200 m² of solid wood ceiling cladding made of silver fir
The work on the sports hall is progressing according to plan – we will continue to keep you up to date! 👀